$16m Nelson’s Rocks Road Cliff Stabilization Project Completed

Workers have stripped 2000 tonnes of loose rock from a crumbling cliff face above Nelson’s Rocks Road, completing a $16 million stabilization project to secure the vital transport link.

The work, which began in November, aims to protect the route following severe storm damage in June and July last year, 1News reported.

The project addresses a critical vulnerability for the top of the South Island.

Rocks Road serves as one of only two connections between Nelson and Tasman and acts as the sole route for heavy vehicles entering the Port of Nelson.

“It literally landed in our lap. It’s not a project we planned to do. It was a project that we needed to respond to quickly,” NZ Transport Agency area manager Rob Service told 1News.

Engineering the unstable terrain

The site sits near the Tahunanui Slump, identified as the largest urban landslide in New Zealand. The road has faced repeated closures due to weather events in 2011, 2022, and again last year, when falling debris narrowly missed passing motorists.

Fulton Hogan project manager Paul Hunter described the site as complex, noting the presence of a 40-metre cliff on one side and heavy traffic on the other.

Crews have secured approximately 10,000 square metres of terrain using nearly 2000 anchors.

“We did find a couple of big rocks that were just sort of precariously sitting there and so we had to take those down,” Hunter told 1News. The finished cliff face now features a large retaining wall at the top and sections covered in concrete to prevent erosion.

Stabilization efforts mesh installation

The stabilization efforts have included installing mesh systems designed to catch falling material before it reaches the road surface. “It basically holds that mesh tight against the surface and then if there was to be anything eroding away it can’t fall directly on to the road,” Hunter said.

Approximately 22,000 vehicles traverse the road daily.

While the construction necessitated lower speed limits and intermittent night-time closures, the NZ Transport Agency expects all restrictions to be lifted next month.

“As a result of this resilience project we’ll leave the cliff face in a much more resilient state than when we arrived on it,” Service said. The project is scheduled for completion by Christmas.

Frequently asked questions about the project

Why was this project necessary for the Nelson region? Rocks Road is the only path for heavy traffic heading into the Port of Nelson or moving between Nelson and Tasman. The NZ Transport Agency noted there was no alternative route available to keep freight moving during the recent weather-related disruptions.

The system uses nearly 2000 anchors to pin mesh against the cliff face.

This design traps loose material and prevents it from falling onto passing traffic, even if the surface behind it begins to erode.

When will the current traffic restrictions end? The lower speed limits and night-time closures are set to conclude next month, with the full project expected to be finished by Christmas.