A P14.6 million skywalk project in Barangay Ibo, Lapu-Lapu City, has again fallen behind schedule, missing a revised completion target of November 2025. This marks the latest in a series of delays for the infrastructure project.
Project History and Delays
Originally slated for completion on November 17, 2024, after a 188-day construction period beginning February 14, 2024, the project experienced multiple suspensions. These interruptions stemmed from issues related to overhead power lines and securing necessary road right-of-way clearances, hindering access to the construction site.
Construction resumed after these issues were addressed, but the November 2024 deadline was missed, along with subsequent revised timelines. As of December 18, 2025, Lone District Rep. Junard “Ahong” Chan stated the contractor, GSixty Construction Services, is now aiming for completion within December of that year.
Current Status and Oversight
Representative Chan recently inspected the skywalk with engineers and reported that roofing has been installed on the steel structure. However, he also indicated that the City Government has raised concerns with the Department of Public Works and Highways (DPWH) regarding the ongoing delays, specifically referencing the previous suspensions due to power line and right-of-way issues.
According to Representative Chan, the DPWH holds full authority over the project’s implementation, including payments, inspections, and the authority to impose penalties. He emphasized that the city government’s role is limited to follow-up and oversight.
Looking Ahead
Failure to meet the latest December target could result in deductions and penalties for the contractor, as stipulated in the project contract. It is possible that the DPWH may investigate any unjustified delays and impose sanctions. Further delays could also lead to increased scrutiny from local officials and the public. A possible next step is for the DPWH to provide a detailed explanation for the continued setbacks and a revised timeline for completion.
Frequently Asked Questions
What is the total cost of the skywalk project?
The skywalk project in Barangay Ibo has a total budget of P14.6 million.
Who is responsible for the project’s implementation?
The Department of Public Works and Highways (DPWH) 6th District Engineering Office has full authority over the project’s implementation.
What caused the initial delays in construction?
Construction was initially suspended due to unresolved issues involving overhead power lines and road right-of-way clearances.
How might ongoing infrastructure delays impact public trust and local development?
Keep reading