Srinagar, Jan 23: A severe winter storm brought down power lines across the Kashmir Division, leaving the vast majority of the region without electricity. The Kashmir Power Distribution Corporation Limited (KPDCL) reported widespread damage to its infrastructure following high-speed winds, heavy snowfall, and rainfall.
Power Grid Collapse
The power demand plummeted to 93 MW around 10:00 PM on January 22-23, 2026, a dramatic decrease from the typical average load of approximately 1650 MW. This decline occurred as faults and damage impacted 33kV and 11kV feeders. Damage was exacerbated by rooftops being blown off and falling onto power lines.
As of morning, 103 of 135 33 kV lines were down or experiencing faults, meaning roughly 24% of the sub-transmission network remained active. At the distribution level, 1275 of 1302 11 kV feeders were similarly affected.
Restoration Efforts Underway
Restoration efforts began immediately, overseen by the Managing Director and Chief Engineer, with support from Superintending and Executive Engineers. By 6:00 PM, approximately 80% of the network had been restored, with a load of 1050 MW recorded. Prioritization was given to essential and vital installations.
Areas Most Affected
The storm’s impact was particularly severe in the districts of Shopian, Kulgam, Baramulla, and Budgam. Restoration work is hampered by approximately 4.5 feet of snow in higher elevations, severely limiting vehicular access. Specific areas experiencing outages include DH pora, Kund, Malwan, and branel-Lammar in Kulgam; Sedow, Reshnagri, Herpora, Kaprain, and Kuch dora in Shopian; and Khanshab, Beerwa, Doodhpathri, and Yousmarg in Budgam.
Damage to a transmission tower at Sheeri in the Delina-LJHP 132 kV Transmission line is also hindering restoration. JKPTCL (Kashmir) is working to restore the network by erecting an Emergency Restoration System (ERS).
KPDCL has stated its commitment to restoring power to all areas by nightfall, with personnel and equipment mobilized to affected regions.
Frequently Asked Questions
What caused the power outages?
Severe gusty winds, incessant rainfall, and heavy snowfall caused faults and damage to 33kV and 11kV feeders, leading to a widespread collapse of the power grid.
How much of the power network was affected?
As of morning, 103 out of 135 33 kV lines and 1275 out of 1302 11 kV feeders were down or under fault.
What is being done to restore power?
Restoration efforts began immediately and are being monitored by the Managing Director, Chief Engineer, Superintending Engineers, and Executive Engineers. Approximately 80% of the network was restored by 6:00 PM.
As restoration efforts continue, will the remaining areas be able to regain power before nightfall?
