Jeddah Tower has reached the 120th floor at a height of approximately 482 meters, according to financial results data released by Kingdom Holding Company. Construction progress includes more than 322,000 cubic meters of poured concrete, marking roughly 72% of the targeted total volume for the structure.
The development also features the installation of over 3,900 facade panels, which accounts for about 14% of the overall panel count. Initial installation work for mechanical, electrical, and plumbing systems continues across the tower, while the designated steel subcontractor for the Sky Terrace project has commenced work on site.
Contract carries 7.2 billion riyals value
The overall construction contract carries a value of 7.2 billion riyals, following an agreement signed in October 2024 between Jeddah Economic Company and Saudi Binladin Group. Kingdom Holding Company noted that approximately 1.1 billion riyals has already been paid for completed structural work under a 42-month implementation window.
Did You Know? Kingdom Holding Company officially announced the resumption of construction work and concrete pouring for Jeddah Tower in January 2025.
Kingdom Holding Co. said Jeddah Tower has reached the 120th floor, with a height of approximately 482 meters.More than 322,000 cubic meters of concrete have been poured, representing around 72% of the total targeted volume.The company’s CEO Talal Ibrahim Al Maiman expects… pic.twitter.com/hYuGN0jIsj
Tower completion expected in 2028
Talal Ibrahim Al-Maiman, Chief Executive Officer of Kingdom Holding Company, expects the tower to reach nearly half a kilometer in height before the end of the current year. He also noted that Jeddah Economic Company continues to display long-term prospects alongside ongoing construction progress.
Analytic projections and executive timelines place the full completion of the Jeddah Tower project in 2028, with the finished structure ultimately designed to exceed 1,000 meters in height.
Jeddah Tower reaches 482 meters height
What is the current height of Jeddah Tower?
Jeddah Tower has reached approximately 482 meters, which corresponds to the 120th floor.
How much concrete has been poured for the project so far?
Construction crews have poured more than 322,000 cubic meters of concrete, representing about 72% of the targeted total.
When is the project expected to be fully completed?
Talal Al-Maiman, Chief Executive Officer of Kingdom Holding Company, expects the entire Jeddah Tower project to reach completion in 2028.