Leyte Governor Carlos Jericho Petilla is calling on the national government to redirect a portion of the flood control budget toward the energy sector to address persistent power shortages in the Visayas. The proposal comes as regional grid alerts continue and experts warn that energy exports from Luzon and Mindanao will soon cease.
Funding Shift for Power Needs
Governor Petilla, a former Department of Energy secretary, argued that the government should prioritize electricity reliability over flood control projects, particularly given current geopolitical tensions and the threat of El Niño.
“The national government would say there is no budget for power, but there is money for flood control projects. Can we take a portion of the flood control budget because this is an immediate concern now?” Petilla said in an interview.
The call for a budget reallocation follows public scrutiny of flood control spending, which has faced allegations of overpriced and substandard projects. During 2027 budget deliberations, Senator Panfilo Lacson highlighted concerns regarding duplicate appropriations for these projects.
Petilla, who served as energy chief during the administration of the late President Benigno “Noynoy” Aquino III, emphasized that securing a reliable electricity supply is an immediate priority. He said that global energy market uncertainties linked to the Middle East conflict, combined with the looming effects of El Niño, necessitate urgent action.

Visayas Grid Faces Prolonged Alerts and Upcoming Supply Gaps
The Visayas power grid has faced recurring red and yellow alerts for at least five months, leaving the region vulnerable to rotational brownouts. “Next year, Mindanao will have a shortfall, so they will no longer export power to us. In 2028, Luzon will also have a shortfall, so they will no longer be able to sell power to us,” Petilla said.
Current supply issues have been exacerbated by the forced outage of the 169-megawatt Therma Visayas Inc. Unit 1 on November 14. Mindanao’s ability to export electricity to the Visayas has been limited by a combination of 463 megawatts in planned outages and 219 megawatts in forced outages.
Other grid pressures include the 135-megawatt Unit 1 and a 103-megawatt unit of Kepco Salcon Power Corp., while the 169-megawatt Therma Visayas Inc. Unit 2 has been operating at reduced capacity.
Proposed Emergency Interventions
To stabilize the grid, Petilla suggested installing 600 battery energy storage systems, with each unit estimated to cost P2.5 million and provide 50 megawatts of capacity. He said that these systems could be operational within 18 months. He also said that rehabilitating aging power plants to restore capacity is an option, though such work could take five years to yield results.

Beyond immediate fixes, the department is targeting 4,000 megawatts of additional renewable energy capacity in 2026 and another 2,000 megawatts in 2027, with 60 projects totaling 4,167 megawatts already completed.
| Energy Source/Facility | Capacity or Status |
|---|---|
| Therma Visayas Inc. Unit 1 | 169 MW (Forced outage since Nov 14) |
| Proposed Battery Systems | 600 units (50 MW each) |
Calls for Executive Action
House Deputy Speaker and Bacolod Representative Alfredo “Albee” Benitez is advocating for the grant of emergency powers to President Ferdinand Marcos Jr. to expedite the implementation of identified energy solutions. Benitez said that bureaucratic delays and red tape have hindered the progress of power projects. He suggested that a ceremonial signing of agreements for identified solutions is currently being considered to move past stalled discussions.
“It cannot be built after a crisis; it must be built before one comes,” Secretary Garin said.
The Department of Energy expects the total completed project capacity across the country to reach 6,587 megawatts by the end of 2026, a figure that includes 5,341 megawatts in Luzon, 733 megawatts in the Visayas, and 513 megawatts in Mindanao.