Dublin City Council confirmed the Merrion Square Park tea rooms will open mid-2027 at a cost of over €6 million.
- The project budget grew from €2.4 million in 2018 to over €6 million.
- Construction began in 2023 following a development period that started in 2015.
- The finished pavilion will be 20 per cent smaller than the original 371-square-metre design.
Budget Growth and Construction Delays
The facility was originally scheduled for completion by the end of 2024. Main contractor Bracegrade faced an 18-month construction delay caused by a contractual dispute.
Work resumed earlier this year following mediation between the local authority and the design team. The council said that the contractor provided a completion window of March or April 2027 for construction and fit-out work, with public opening expected a month or two later.
Dublin City Council initially estimated potential final costs could reach €7.5 million, though officials now state they do not expect the bill to hit that threshold. The local authority attributed the rising expenses to pandemic impacts, extended project duration, construction inflation, statutory compliance requirements, and contractual disputes.
DCC said the tea room’s costs reflected the “cumulative impact of Covid, extended programme duration, construction inflation, statutory compliance requirements, contractual disputes and associated delay costs over the period of the project.”
Council Scrutiny and Governance Questions
Independent Councillor Mannix Flynn criticized the expenditure during an interview, calling it a vanity project amid wider municipal pressures. The development includes a café with an outdoor terrace, public toilets, and a foyer functioning as an exhibition space.

“It’s the most expensive tea room in the history of the State,” Mannix Flynn said.
“We’re not in a crisis of tea, we’re in a crisis of housing and while I can’t get a window fixed in a block of flats, Dublin City Council seems to be able to come up willy-nilly with millions for unnecessary tea rooms,” Flynn said.
Fine Gael Councillor Danny Byrne also criticized the spending, noting that internal documents obtained via Freedom of Information show the council’s Corporate Project Governance Board suspended the project in 2019 over scope and cost concerns before it restarted the following year.
“It’s huge money for a tea room, a public toilet and some artist space.” Danny Byrne said.
“There seems to be a disregard for the taxpayers’ money,” Danny Byrne said.
But it was restarted the following year. Seven years later I’m still looking for answers,” he said.
In response to member concerns, Dublin City Council announced it will appoint an external consultant to review project governance, reporting arrangements, and the exact causes of cost overruns and delays.
Conservation Context and Next Steps
A Conservation and Management Plan published for the square in 2014 first identified the need for park tea rooms and public toilets. The structure stands near the playground and the Oscar Wilde statue beneath the canopy of 200-year-old trees.
Donough Cahill, Executive Director of the Irish Georgian Society, defended the architectural ambitions of the project for the south Georgian quarter park, which attracts up to a million visitors annually.
Independent Councillor Mannix Flynn, who has served on Dublin City Council since May 2009 representing the South-East Inner City and later Pembroke–South Dock local electoral areas, criticized the Merrion Square tea rooms project as a “vanity project” and the “most expensive tea room in the history of the State.”
He contrasted the over €6 million spend with the housing crisis and his inability to get basic repairs for flat complexes, highlighting a pattern of challenging municipal expenditure priorities.
“Trying to achieve that standard of excellence is something that’s very understandable,” Donough Cahill said.