Titirangi Road Set to Reopen After Nine-Month Closure Far Exceeding 10-Week Plan

Tanekaha Road in Titirangi is set to reopen this weekend after a nine-month closure that far exceeded the original 10-week timeline, Auckland Council confirmed on Friday. The cul-de-sac has been shut from 8.30am to 5.30pm on weekdays since the 2023 storm damage, forcing nearly 300 residents to park at French Bay and climb a steep track to reach their homes.

Auckland Council’s programme director for flood recovery, transport and infrastructure, Jeremy Pellow, said the resealing work was on track to finish Friday, with the road due to reopen over the weekend. The council had originally advised a 10-week closure and estimated the repair would take six months, RNZ reported.

Why did the repair take nine months instead of ten weeks?

Pellow said ground conditions were worse than expected, rock drilling took longer than planned, and a section of an old retaining wall required replacement. He said the extensions were necessary to provide a safe, long-term solution and to maintain safety for the homeowner at the top of the slip.

How have residents managed daily life during the closure?

Residents drive to French Bay, park, and walk up a steep stair track — a round trip some make multiple times a day. Zoe Hawkins, a resident, told RNZ the arrangement works for the fit but not for everyone.

“We’ve got a couple of people having cancer treatment. If they need to go and get chemo, it often means they have to be out for the full day, they can’t get home,” she said.

Signage of Tanekaha Roadworks
Photo: rnz.co.nz

Paul Smith has been housebound for a week and a half after spraining his ankle on the track. “I’ve been isolated in my home… I cannot drive out during the day and I cannot go and park my car anywhere because I would have to walk to the car,” he said.

Susie Cunningham, a doctor at Starship Children’s Hospital, said she often wakes before 8.30am to move her car so she can leave for shifts. “So often I have four or five hours’ sleep, which you can kind of handle for a few months but for nine months now it gets quite tiring,” she said.

What has the disruption cost households?

Hawkins said residents calculated roughly $370,000 in shared out-of-pocket costs — about $3,700 per household — covering taxis, extra travel, and café waits while the road was closed. “That didn’t include the time cost,” she said.

How was communication handled?

Residents said extensions were announced piecemeal as they arose. “Each extension has been communicated as it arises. So I’m not sure why that is, but that’s the way that we’ve received the news has been piecemeal,” Hawkins said.

Helen Sodeau said she would have liked a realistic timeframe from the outset. “I think from the outset more investigation should have gone in so we could have had a realistic time frame,” she said.

Where does this project sit in the wider storm recovery?

Auckland Transport has completed 793 road fixes since the 2023 storms; four remain in progress, including Tanekaha Road. Pellow thanked residents for their patience and tolerance.

“It’d be nice to have life back to normal,” Hawkins said.