Three dismissed managers at Sénégal Numérique SA dispute the stalled PASSANT fiber-optic network project with executive leadership.
The controversy centers on the PASSANT initiative, which was launched in August 2019 to construct a 339.8-kilometer transport network, connect over 300 administrative buildings to fiber optics, and install 125 public Wi-Fi points.
According to an audit by the cabinet ADOC for the Autorité de régulation de la commande publique (ARCOP), the contract was awarded through a spontaneous offer to the Spanish firm Liteyca S.L. for a total cost of 50,000,838,369 FCFA inclusive of tax.
Financed by CBAO and Banco Santander with an initial service order dated January 15, 2019, the project was granted two time extensions without financial impact. Although the scheduled completion date was pushed to April 13, 2024, field visits in April 2024 revealed that no provisional acceptance had occurred and the work remained at a complete standstill.
The ARCOP audit released in November 2024 highlighted several administrative and financial discrepancies during the execution period. Auditors reported 4,513,438,738 FCFA disbursed for management and supervision fees at startup without guarantees on their utilization, approximately 5 billion FCFA in unapplied delay penalties, and 69 million FCFA paid for unvouched work outside the original estimate.
Did You Know? The PASSANT fiber-optic network contract was initially established under the direction of former general manager Cheikh Bakhoum before Isidore Diouf took over leadership of Sénégal Numérique SA in May 2024.
Audit Findings and Financial Discrepancies
While the official ARCOP audit said that the physical structures were generally compliant with initial studies, it characterized overall execution as unsatisfactory and identified a 22-month delay. The report also detailed high unit costs for points of presence and fiber installation, prompting a recommendation for an in-depth review.
Sénégal Numérique SA stated in the report that certain tasks were not finalized by Liteyca subcontractors, though auditors countered that those exact deliverables were accepted and paid for by the public enterprise. In response to the ARCOP recommendations, executive management commissioned a second independent technical audit that was not made public.
According to the company’s response published on November 15, the unpublicized evaluation cited an unfavorable opinion on contract execution, pointing to 3.4 billion FCFA in non-conformities out of 6.9 billion FCFA in civil engineering works. Management calculated total projected losses and damages at approximately 24 billion FCFA, encompassing unexercised contractual rights, price overvaluation, and future network depreciation.
Dismissed personnel contest terminations through labor inspection
The dismissed personnel and a collective known as the Réseau des Sénégalais pour le numérique et la souveraineté informatique (RNS) contested the dismissals as irregular. The RNS issued a statement on November 12 accusing the general manager of rejecting reinstatement requests issued by the supervisory ministry, though the statement relied primarily on conditional phrasing without including management commentary.
Management further said that the three affected workers brought their case before the labor inspection office on November 11, 2026, where officials reportedly estimated that there was no right to reinstatement and closed the case.
On the judicial front, Sénégal Numérique SA filed three separate complaints with civil party constitution covering public fund embezzlement, fraud involving public funds, forgery, and breach of trust. Additional oversight measures include referrals to the Court of Accounts and an ongoing investigation by the Division des investigations criminelles (DIC), while all targeted individuals maintain a legal presumption of innocence.
Questions about PASSANT project costs and employee dismissals
What was the total cost of the PASSANT project?
The project was awarded for a total amount of 50,000,838,369 FCFA including tax, according to the official ARCOP audit data.
What legal steps has the company taken regarding the project?
Sénégal Numérique SA filed three formal complaints involving allegations of public fund embezzlement, fraud, forgery, and breach of trust, alongside referrals to the Court of Accounts and the DIC.