Enshore Subsea has completed the installation of the second of two 220 kV three-phase export cables for the Inch Cape offshore wind farm, utilizing the cable lay vessel CMOS Installer operating out of the Port of Blyth, according to project disclosures.
Cable Installation Details and Vessel Operations
The second of two export cables was installed in three 28-kilometer sections by Enshore Subsea using the CMOS Installer vessel. According to project details, the work required two offshore joints executed by specialists onboard the Normand Cutter. The cables were subsequently buried in the seabed using the ENS1100 hybrid trenching vehicle, with final rock placement scheduled to follow.
Ningbo Orient Wires & Cables Co. Ltd manufactured the 2000 mm² cables. Weighing nearly 140 tonnes per kilometer, they rank among the largest alternating current export cables globally, with a total of 170 kilometers installed across the scope.
Did you know? The Inch Cape offshore wind farm export cables weigh approximately 140 tonnes per kilometer, making them some of the largest AC export cables deployed worldwide.
Power Transmission Route to the National Grid
The parallel export system is designed to transmit electricity from the 1.1-gigawatt wind farm’s offshore substation platform to a new onshore substation situated at Cockenzie, East Lothian. From there, the power will route directly into the national grid. Project operators confirmed the infrastructure will undergo energization over the coming weeks, targeting first power toward the end of the year.
“The completion of this crucial link between the offshore and onshore substations is another major achievement for the project and testament to the excellent collaboration between the Inch Cape team and our contractors, particularly Orient Cable and Enshore Subsea,” said John Hill, Inch Cape Project Director.
Contractor Perspectives and Technology Deployment
Pierre Boyde, CEO of Enshore Subsea, highlighted the performance of specialized equipment during the shallow-water operations. The deployment relied heavily on the ENS1100 hybrid trencher, which was purpose-built for the project.

“It demonstrates Enshore’s ability to fast-track complex projects, our strength in shallow-water operations, and the excellent performance of ENS1100, our latest hybrid trencher, purpose-built for the project,” Boyde stated.
Parallel offshore construction continues at the site. Inch Cape recently finalized its monopile and transition piece installation. Current activities involve array cable laying by the new-build vessel Altera and jacket foundation pin pile installation using the Alfa Lift. Meanwhile, components for the site’s 15-megawatt turbines are arriving at the Port of Dundee for tower assembly ahead of offshore installation.
Project Timeline and Generation Capacity
The overall development remains on schedule to achieve full commercial operations in 2027. Jointly owned on a 50/50 basis by ESB and Red Rock Renewables, the completed wind farm is projected to generate nearly five terawatt-hours of energy annually—an output calculated to power half of the homes in Scotland.

Frequently Asked Questions
What vessels were used to install the Inch Cape export cables?
Enshore Subsea utilized the cable lay vessel CMOS Installer, operating out of the Port of Blyth, along with the Normand Cutter for offshore joints and the ENS1100 hybrid trenching vehicle for seabed burial.
Who manufactured the export cables?
The 2000 mm² cables were manufactured by Ningbo Orient Wires & Cables Co. Ltd (Orient Cable).
When is the wind farm scheduled for full commercial operations?
According to project timelines, the development remains on track for full commercial operations in 2027.
How much energy will the completed wind farm generate?
Once operational, the facility will generate nearly five terawatt-hours of energy each year, supplying enough electricity to power half of the homes in Scotland.