Far North Solar Farm Placed in Receivership Over Debt

Far North Solar Farm Ltd, the company behind a proposed Mackenzie Basin solar farm, was placed into receivership on November 18 after its former joint venture partner moved to recover debt.

  • Receivers appointed November 18 under a 2021 General Security Deed
  • Fast-track application for The Point suspended in August over unpaid fees
  • Government green bank committed $78 million but never advanced funds
  • Community opposition cited misuse of fast-track legislation

Aquila Clean Energy SG Holdco Pte. Ltd appointed Stephen Keen and Stephen White of Teneo Financial Advisory New Zealand as joint receivers pursuant to a General Security Deed signed in 2021. The deed covered a joint venture that commissioned the Pukenui solar farm in Northland before the partners agreed to separate in January, with Aquila stating both parties would “pursue their perspective strategic priorities independently.”

Under the split, Far North Solar Farm retained developments in Greytown, the Mackenzie, and other South Island areas, according to Aquila’s website. Far North Solar Farm was also in debt to Aquila under the security agreement, leading to the receivership.

The company’s flagship project, The Point — a proposed 40MW solar farm on the northern shore of Lake Benmore — had already stalled. The Environmental Protection Authority suspended processing on August 21 after Far North Solar Farm failed to pay costs associated with the consenting process. A company spokesperson defended the move at the time, saying Far North Solar Farm intended to pay its fees and progress the project.

“They do appear to be gaming the system and not using it as intended,” Murdoch said. Far North Solar Farm firmly denied the characterisation. Residents had discussed introducing specific land overlays to protect the area's natural scenery and forming sustainability coalitions similar to those in Southland and Queenstown.

New Zealand Green Investment Finance (NZGIF) announced a $78 million loan facility for Far North Solar Farm in 2024 covering five developments generating around 1.13 gigawatts. Homewood told RNZ’s Morning Report most sites would be under construction within 12 to 18 months.

The company never received any of the committed funds.

NZGIF was created in 2018 under Labour’s confidence and supply agreement with the Green Party. The agency previously wrote off $113.3 million in financing after BlackRock pulled support from residential solar firm Solar Zero, leading to its liquidation.

Photo: Chris Lynch Media

Far North Solar Farm also held consents for a 144MW solar farm at Waipara in North Canterbury, which attracted 158 submissions with 125 opposed, and a 175MW project at Greytown in the Wairarapa that received resource consent in June subject to considerable conditions. A Tasman district application near St Arnaud has had its base deposit fee unpaid for more than two years.

The Waipara Valley Community Collective Incorporated filed an appeal against the Waipara consent decision on November 3.

Receivers now control the company’s secured assets and can exercise rights under the security agreements and the Receiverships Act 1993. Far North Solar Farm did not respond to Newsroom’s questions on receivership in time for publication.