The Galecopperbrug on the A12 toward Arnhem reopened at 5 a.m. on Monday, a day earlier than planned, after repairs to two steel main girders progressed without technical setbacks, Rijkswaterstaat said.
The early reopening averts the heavy congestion Rijkswaterstaat had warned would peak on Monday with delays exceeding 60 minutes, compounded by regional public transport strikes, NOS reported. About 110,000 vehicles use the bridge daily toward Arnhem, making it the second-busiest bridge in the Netherlands, according to Rijkswaterstaat. “The work we carry out at the Galecopperbrug is technically complex,” a Rijkswaterstaat spokesperson said.
“That is why we account for possible risks and unexpected setbacks in the planning. The work has, however, progressed very smoothly, allowing the bridge to reopen earlier.”
The closure began Friday at 10 p.m. and was originally scheduled to last until Tuesday at 5 a.m. Crews replaced a 3-by-1-meter section of each girder to permanently fix deformations discovered during finishing work in 2025, De Telegraaf reported.
Second closure still set for December
A second weekend closure remains scheduled from Friday, Dec. 4 at 10 p.m. to Tuesday, Dec. 8 at 5 a.m., Rijkswaterstaat said. The agency is evaluating the first work period this week to determine whether the December closure can be shortened.
“It is still unclear whether the time gain will affect the second closure,” a spokesperson told De Telegraaf. “Next week the first weekend will be evaluated. Depending on the outcomes, it will be examined whether the planning for the multi-day closure from Dec. 4 to 8 will be adjusted.”
Rijkswaterstaat, as the Directorate-General of the Ministry of Infrastructure and Water Management, holds the authority for the practical execution of public works and water management, including the construction and maintenance of roads such as the A12 Galecopperbrug. The regional service RWS Midden-Nederland (located in Utrecht and Lelystad) manages this second-busiest bridge in the Netherlands, carrying about 110,000 vehicles daily toward Arnhem.
Rijkswaterstaat’s specialist service RWS Programmes, Projects and Maintenance (RWS PPO, located in Utrecht) oversees the planning and coordination of such major maintenance projects.