An Coimisiún Pleanála has granted planning permission for the expansion of Google Ireland Limited’s data centre at Grange Castle Business Park in south Dublin. The approval follows a two-year dispute after South Dublin County Council initially refused the proposal in August 2024, citing concerns over electricity grid capacity and a lack of on-site renewable energy. The project represents the third phase of the company’s campus development.
Conditions Attached to the Grange Castle Expansion
While the planning body overturned the local council’s refusal, the approval is contingent upon several strict conditions. Google must provide evidence of engagement with power purchase agreements before construction begins. The company must also use renewable fuel for all backup power generators on the site.
To address broader sustainability concerns, the approval also mandates that Google implement incentives for staff to utilize public transport, walking, and cycling. The developer must also enhance the ecological value of the 50-acre site and carry out specific mitigation measures identified in the project’s environmental impact assessment report.
The Dispute Over Grid Capacity
The core of the planning conflict centered on the availability of electricity. South Dublin County Council’s original refusal in 2024 argued that the regional grid lacked the capacity to support the 72,400sq m facility. Google successfully challenged this in its appeal, noting that it had already secured a formal grid connection agreement with EirGrid in 2021.
Google’s appeal argued that the local council was not the appropriate authority to determine the technical capacity of the national electricity network. An Coimisiún Pleanála accepted this position, though the decision does not guarantee an immediate start to construction. The project remains subject to potential judicial review in the coming weeks.

Did you know? Data centres accounted for nearly 25 percent of all electricity consumed in Ireland in 2023. This is a significant increase from 2015, when these facilities used approximately 5 percent of the nation’s total supply.
Infrastructure Demands and Public Sentiment
The expansion is designed to support the growing demand for ICT services within Ireland. A spokesperson for Google stated that the company remains committed to investing in local infrastructure, describing data centres as an “essential part of Ireland’s ambitious digital economy.” Without this extension, the company previously warned it would struggle to meet the rising service requirements of its customers.
Despite the approval, the project faces heightened public scrutiny. A recent Irish Times/Ipsos B&A opinion poll indicated that a large majority of the public supports a pause in the construction of new data centres. This tension reflects global trends; as AI services drive a surge in computing power, the industry faces increasing environmental and electricity-related opposition in the United States and other international markets.

Frequently Asked Questions About the Grange Castle Project
Why was the data centre initially refused?
South Dublin County Council rejected the plans in August 2024, citing insufficient electricity grid capacity and a lack of significant on-site renewable energy to power the proposed facility.
What has changed to allow the project to move forward?
An Coimisiún Pleanála overturned the refusal after determining that Google had already secured a valid grid connection from EirGrid. The approval is now subject to new conditions regarding renewable energy usage and site ecology.
Will construction start immediately?
No. The decision by An Coimisiún Pleanála may still be subject to a judicial review, which could delay the start of construction on the third phase of the campus.
How many jobs will the expansion create?
The development is expected to support hundreds of roles during the construction phase and create up to 50 permanent jobs once the data centre is fully operational.