The total closure of Riga’s Cable-Stayed Bridge during its upcoming reconstruction would cost the Latvian economy approximately 700,000 euros per day, according to Economy Minister Viktor Valainis. Speaking on the LETA podcast “Politicians! What Was That Even?”, Valainis stated that traffic across the Daugava River must be maintained throughout the repairs to prevent severe financial and logistical burdens for the capital and the country as a whole.
Bridge Tender Details and Reconstruction Timeline
Preparations for the multi-million euro overhaul of the Cable-Stayed Bridge are already underway. The supplier consortium “Vanšu tilts” won the procurement tender after a complaint from a competing participant was reviewed, and a contract has now been signed for design and construction work totaling 69.8 million euros excluding VAT, according to source reports. Separately, reporting from Diena notes that the total cost is valued at 70 million euros excluding VAT, with the main construction phase scheduled to span from the third quarter of 2027 to the second quarter of 2029.
Funding allocations are distributed across multiple years. Budget planning sets aside up to 6.7 million euros for the project in 2026, up to 42 million euros in 2027, and another up to 35.76 million euros in 2028. The design phase is currently ongoing and is slated for completion by June 2027. Once work begins, the extensive project will replace the road surface, replace all stays and update their protective shells, restore barriers, and build separate zones for pedestrians and cyclists.
Traffic Disruptions and Economic Impact
The daily closure of the bridge carries high stakes for thousands of local residents, public transport operators, and freight carriers who rely on the crossing. According to Riga Mayor Viesturs Kleinbergs, speaking during the 900 seconds broadcast, planners are weighing the possibility of completely closing the bridge to private transport during the most difficult phases of the work. Current plans generally aim to maintain traffic in at least one lane in each direction during most of the construction, though short-term total closures remain a possibility. The Riga City Council plans to release detailed detour schemes and traffic restrictions in the fourth quarter of this year.
Did You Know? Economy Minister Viktor Valainis proposed purchasing a temporary modular bridge rather than renting one, suggesting that after the Riga project concludes, the structure could support repairs elsewhere in Latvia or enter state material reserves for civil protection and defense. Similar modular bridges have previously been deployed during roadworks in Salacgrīva and Daugavpils.

To offset transit bottlenecks, the city intends to develop alternative transport options. These plans include establishing new Park&Ride parking facilities on both sides of the Daugava River, completing the fourth phase of the Southern Bridge, and potentially launching rail services to Bolderāja. SEB Bank economist Dainis Gašpuitis notes that while prolonged repairs will inevitably complicate city mobility, the broader economic impact is expected to remain largely local to Riga, provided alternative routes are organized and communicated clearly.
According to the Latvian Employers’ Confederation, service, trade, catering, logistics, construction, and healthcare sectors face the highest risk of operational delays, making timely public communication and robust detour planning critical to mitigating disruptions.
Frequently Asked Questions
How much will the reconstruction project cost?
The winning consortium “Vanšu tilts” secured the contract for 69.8 million euros excluding VAT, with overall project estimates cited at approximately 70 million euros excluding VAT across a timeline extending into 2029.

What alternatives are authorities planning for motorists?
The city intends to create new Park&Ride lots on both banks of the Daugava, integrate the fourth phase of the Southern Bridge once completed, and explore rail services to Bolderāja, alongside maintaining at least one lane of traffic in each direction during most of the project.
Why is maintaining a crossing over the Daugava considered vital?
Economy Minister Viktor Valainis estimates that a total closure of the Cable-Stayed Bridge would cost the national economy roughly 700,000 euros per day due to added travel time and business expenses for freight, public transit, and residents.
How will your daily commute or business operations be adjusted once the Cable-Stayed Bridge reconstruction begins?