Utility installation work on Boulevard Bara in Tournai caused a simultaneous rupture of a high-voltage cable and a water main on Tuesday evening. The incident, which occurred shortly after 6:00 p.m., resulted in power and water outages for residents living near the Maison de la Culture, according to reports.
Emergency response and site containment
Local authorities deployed a significant emergency response to the scene to manage the infrastructure failure. The police of the Tournaisis secured the area by closing a section of Boulevard Bara, while teams from Ores and the SWDE arrived to address the utility damage. Firefighters from the Wapi rescue zone also assisted with the operation.
While Ores crews were able to restore electricity to some affected sectors of the city following the incident, the water main break caused localized flooding. A private residence on Rue Jean Noté sustained water damage, requiring firefighters to pump out a garage. No residents were required to evacuate their homes as of Tuesday night.
The disruption was linked to ongoing work regarding the installation of fiber optic cables in the area, which inadvertently struck underground utility lines.
Infrastructure projects involving high-speed connectivity often require extensive excavation in dense urban environments. This incident highlights the inherent risks of “utility congestion,” where legacy water and power lines sit in close proximity to new telecommunications infrastructure, creating a complex environment for contractors and municipal emergency services.
What happens next
Frequently Asked Questions
What caused the outages in Tournai?
The outages were caused by fiber optic installation work on Boulevard Bara that damaged both a high-voltage electrical cable and a water main.

Were residents evacuated during the incident?
No, authorities did not deem it necessary to evacuate any residents on Tuesday evening, despite flooding in a garage on Rue Jean Noté.
Is electricity currently available in the area?
While the incident initially cut power to the area around the Maison de la Culture, Ores teams were able to restore electricity to other affected sectors of the city.
How should city planners balance the need for modern fiber optic infrastructure with the risks posed to existing underground utility networks?
Related reading