- Staff chose Modified Option 2 as the locally preferred alternative for the LA River Path project.
- The alignment carries a preliminary $872 million cost estimate with $433 million in Measure M funds available.
- Two initial segments totaling 5.5 miles would be built first; a 2.5-mile downtown gap would use city streets as an interim connection.
Metro staff released their recommendation, identifying Modified Option 2 as the locally preferred alternative for the LA River Path project, The Source reported.
The alignment would close the break between existing trails in Elysian Valley and Vernon, completing a 51-mile walking and bicycling corridor from the San Fernando Valley to Long Beach.
Alignment follows riverbank to reduce cost
Rather than relying heavily on elevated structures, the preferred design places more of the path on top of the riverbank or incised into the channel wall, with elevated sections only where needed to cross rail lines, roads and the river itself, STM Daily News reported. The corridor is constrained by freight and passenger rail infrastructure, utility towers, freeways and roughly 30 bridges.
Staff said the revised approach reduces permitting complexity and construction costs while preserving direct links to nearby communities and transit.
The plan includes three new river crossings and 10 access points — seven on the east bank and three on the west — with two more possible at Seventh Street and near Bandini and Soto streets if funding is identified.

Phased construction leaves downtown gap on city streets
Together they cover 5.5 miles of the eight-mile gap. Protected bike lanes already in place or planned by the City of Los Angeles would serve as an interim link across the remaining 2.5-mile downtown stretch between Broadway/Spring Street and Sixth Street until the central river segment can be funded and built, STM Daily News reported.
That means part of the initial continuous route would run on city streets rather than along the river.
Funding gap persists
Modified Option 2 carries a preliminary construction estimate of $872 million in 2025 dollars. Metro has approximately $433 million available through Measure M, leaving a gap of about $439 million, STM Daily News reported. The proposal is less expensive than the five full-gap alternatives evaluated in the Draft Environmental Impact Report released in December 2025, which were estimated at roughly $1 billion to $1.2 billion.
Approving the locally preferred alternative would give Metro a defined project to pursue state and federal funding programs and allow design work, value engineering and negotiations with other public agencies to continue, STM Daily News reported.
Governance and maintenance unresolved
Metro holds little of the land needed for the project and would not be responsible for long-term maintenance and operations, Urbanize LA reported. The Los Angeles County Flood Control District is set to lead a governance model study to consider how the path could be managed over the long term.
Both the Metro Board’s Planning and Programming Committee on Nov. 18 and the Executive Management Committee on Nov. 19 considered the locally preferred alternative, The Source reported. The full board is scheduled to vote Dec. 3.