The UK’s largest AI supercomputer project in Loughton, Essex, will miss its planned 2027 launch date and could face delays into the mid-2030s due to severe power supply constraints. Announced by Keir Starmer’s government in 2025 as the country’s largest sovereign AI datacentre, the site is being built by the UK-based startup Nscale, which is seeking a $35bn (£26bn) flotation this year.
Power Supply Constraints and Grid Limitations
UK Power Networks (UKPN), the distribution network operator responsible for connecting the Loughton site, has reportedly informed Nscale that the local electrical grid cannot supply sufficient power until the early to mid-2030s. The delay was first reported by the AI industry newsletter Morning Intelligence. The Loughton site is seeking up to 90MW of capacity, an amount equivalent to the energy consumption of approximately 315,000 homes. While Nscale has stated that it is “committed to the project” and has successfully cleared the planned location—which the Guardian revealed in March was still an operational scaffolding yard—the energy hurdle highlights mounting barriers for major computing infrastructure.
Did You Know? In June, energy regulator Ofgem revealed a massive queue of 315 datacentres waiting to connect to the National Grid, representing 73GW of demand—vastly exceeding the peak energy demand for the entire country of 45GW.
Grid-Level Bottlenecks and National Energy Demands
The power shortage affecting Nscale reflects a broader systemic logjam across the UK electricity network. A UKPN spokesperson explained that schemes with large energy demands often require extensive infrastructure work at a National Grid level before they can operate safely, noting that many datacentres await works on the wider national electricity transmission network. Meanwhile, National Grid stated that it is continuing to work closely with the government-owned National Energy System Operator (NESO), distribution network operators, and customers to identify opportunities to accelerate connections where possible and support economic growth.

Future Outlook and Potential Mitigations
To overcome the lengthy wait for grid connections, Nscale is investigating alternative solutions, including whether the company can generate power onsite and whether it can find ways to speed up the connection process. If these mitigation strategies fail to shorten timelines, the project’s operational debut could remain pushed back into the next decade, altering the deployment schedule for major computing resources that serve as the central nervous system of AI technology such as chatbots.
Frequently Asked Questions
What caused the delay at the Loughton supercomputer project?
The project faces delays because UK Power Networks informed developer Nscale that the local electrical grid cannot supply sufficient power until the early to mid-2030s.

How much power does the Loughton datacentre require?
The site is seeking up to 90MW of capacity, which is equivalent to the energy consumption of about 315,000 homes.
What is Nscale doing to address the power shortage?
Nscale has stated it is committed to the project and is currently investigating whether it can generate power onsite and whether it can speed up the connection process.
What impact might these grid connection delays have on other large-scale technology developments across the country?