On Friday, November 13, 2026, the Federal Aviation Administration ordered a nationwide ground stop after a newly replaced router at a remote Arkansas facility flooded the agency’s communication network with data.
The four-hour shutdown, which ranks as the largest air traffic disruption of its kind since the September 11, 2001 terrorist attacks, forced carriers to scramble while investigators traced the source of the failure, according to AP News. The work was carried out by an engineer from L3Harris who had accessed a facility serving air traffic control centers in southern Arkansas.
Did You Know? L3Harris notified the Federal Aviation Administration on November 9, 2026, of its intention to replace an aging router at the remote facility in El Dorado, Arkansas, with the work scheduled to start at 9:00 a.m, according to Cnn. on Friday, November 13.
Supervision and Policy Disputes After the Router Replacement
Sources familiar with the room operations and representatives from the Professional Aviation Safety Specialists union said that the assigned agency technician merely escorted the contractor inside and did not monitor the technical work.
Elizabeth Doherty, a spokesperson for the union representing Federal Aviation Administration technicians, said that the employee’s instructions consisted “simply in permitir el acceso del contratista al edificio”, adding that the worker “no tenía indicaciones de ayudar ni colaborar de ninguna manera” and that no union-represented employee was asked to conduct a risk assessment for the update, as reported by the news media.
The relaxed oversight framework stems from a March 2025 internal memorandum designed to speed up modernization efforts under a 12.5-billion-dollar funding package, according to sources cited in reporting. Under the revised policy, the agency shifted from approving maintenance requests to simply receiving notifications, meaning “dichos trabajos se llevarán a cabo sin necesidad de aprobación de la FAA”.
Hannah Walden, a spokesperson for the aviation agency, defended the policy change by asserting it “no altera en absoluto la supervisión; cambia la prioridad del trabajo que debe realizarse”. Walden later clarified in a supplementary statement that the escort is responsible only for facilitating access and departure, noting that because the hardware belongs to the vendor, the escort “no está presente mientras el técnico realiza su trabajo”.
Duffy criticizes L3Harris then softens tone on contractor
Transportation Secretary Sean Duffy criticized the vendor publicly on Saturday, November 14, 2026, stating: “Necesitamos que L3Harris, o quienquiera que nos haya suministrado ese enrutador, haga un mejor trabajo”. Duffy added that “muchos de nuestros contratistas y socios aceptan nuestro dinero pero nos ofrecen un servicio realmente deficiente. Punto final”.
By Tuesday, November 17, 2026, Bedford adopted a more conciliatory tone during a press conference, describing the contractor who replaced the equipment as an “ingeniero certificado y altamente capacitado, exveterano de la Fuerza Aérea”. L3Harris confirmed in a statement that it is “colaborando con la FAA en su investigación para comprender las condiciones que condujeron a la paralización del tráfico aéreo nacional el 13 de noviembre”.

The incident has intensified legislative scrutiny regarding how billions in infrastructure funds are spent. Lawmakers have questioned the administration’s request for additional financial allocations while investigations into the router failure continue.
FAA orders nationwide ground stop after router failure
When did the nationwide ground stop take place?
The Federal Aviation Administration ordered the nationwide ground stop on Friday, November 13, 2026, after a newly installed router triggered severe communication problems across the agency’s network.
What specific equipment failure caused the disruption?
A replacement router installed by an L3Harris contractor at a remote radiocommunications facility in southern Arkansas flooded the aging Federal Aviation Administration network with an excess of data, disrupting aircraft communications and radar signals.
L3Harris Technologies, formed by the 2019 merger of L3 Technologies and Harris Corporation, became the sixth-largest U.S. defense contractor. The combined entity traces its roots to the Harris Automatic Press Company, founded in 1895, and L-3 Communications, created in 1997 from former Lockheed Martin units. Headquartered in Melbourne, Florida, the company provides avionics, tactical radios, and night vision systems to government and commercial sectors.
What policy change preceded the incident?
A memorandum issued in March 2025 streamlined maintenance protocols by allowing telecommunications providers to submit work notifications rather than formal requests, eliminating the requirement for prior agency approval on routine updates.