Tauranga City Council has spent more than $5 million responding to the fatal January 22, 2026 landslide at Mount Maunganui, according to financial data released by the council. Six people died when a large chunk of the maunga gave way after a night of heavy rain, collapsing onto the neighbouring Mount Maunganui Beachside Holiday Park.
Council Financial Breakdown and Remaining Reserves
The total expenditure of over $5 million has come out of a $7 million risk reserve approved by Tauranga City Council (TCC), leaving $1.81 million in remaining funding available, according to the financial table presented as part of a council meeting. Additional coverage notes that a state of emergency was declared across the Bay of Plenty region on January 21, 2026, after Tauranga recorded 199.3mm of extreme rainfall, followed by another 96.1mm on January 22, triggering 42 landslides on Mauao and widespread infrastructure damage across the city.
According to the TCC financial table, the response costs are divided into three specific categories:
- Initial weather event response: Physical works and equipment hire totaled $446,144; travel, accommodation, and welfare costs reached $78,264; and trauma support services cost $17,515.
- Ongoing recovery of Mauao: Security expenses totaled $733,923; professional and expert advice cost $1,084,045; and recovery staff expenses reached $226,101.
- Post-event reviews and legal support: Professional and expert advice totaled almost $1.7 million.
External Review Findings and Council Apology
Last month, an external review commissioned by TCC and conducted by retired High Court judge Paul Davison found that the six deaths caused by the landslide were avoidable, stating that “this tragedy was, in the end, preventable,” according to council documents. The review examined the decision-making process and council systems in place around the time of the tragedy, operating separately from ongoing inquiries by the Government and WorkSafe.
In response to the findings, Tauranga mayor Mahé Drysdale apologized to the families for the “failings” of the Council and stated that the local authority accepted all of Davison’s recommendations. “Today, we acknowledge the lives lost at the holiday park. Our entire community continues to feel the deep and lasting effects of this tragedy, yet our primary focus remains with those who perished and their loved ones who carry the burden of that absence every single day,” Drysdale said at a media conference announcing the findings. “I extend my most heartfelt sympathy to all of you. We appreciate your endurance, your bravery, and the dignity you have maintained throughout this unimaginable ordeal.”
Recovery Progress Reports and Planned Improvements
As part of today’s council meeting, a recovery progress report and a Quantitative Landslide Risk Assessment covering the Beachside Holiday Park, Mount Hot Pools, and Mount Maunganui Lifeguard Service building are being presented. According to agenda minutes, the recovery progress report recommends that the Council endorse an Organisation Improvement Programme with a priority focus on preventing loss of life and serious harm, noting that “there is considerable work required to improve culture, processes and systems and partnerships right across the organisation.”
Tauranga City Council has outlined several improvements already put in place, including Trigger Action Response Plans (TARPs) around various sites in the city such as Mauao, alongside improved response procedures for adverse-weather events. Police officially stood down their recovery operation at the landslide site on February 1, 2026, handing the site over to a council-led recovery phase to demobilise work, assess damage, and work toward the safe reopening of Mauao in partnership with the Mauao Trust. Tangata Whenua have also lifted the rāhui previously placed over parts of Waikorire (Pilot Bay) and Hīnekite (Mount Main Beach).
Future Outlook and Scenario Analysis
As the Council moves forward with its recovery operations and financial evaluations, several next steps could emerge based on the current documentation. The Council is likely to debate and potentially endorse the recommended Organisation Improvement Programme during today’s meeting to address the cultural and systemic shortcomings identified in the Davison review. Additionally, remaining funds from the $7 million risk reserve—currently standing at $1.81 million—may face further drawdowns as expert advice, legal support, and ongoing site remediation continue around Mauao.