Ruter Announces Extensive T-Bane Closures and Buss Replacements in 2025
Oslo, Norway – Ruter, the public transport authority in Oslo, has announced plans for significant T-bane closures and bus replacements across various sections throughout 2025. The company acknowledges that these closures will create inconveniences for many passengers but assures that they are necessary for major upgrades.
Three Major Projects in 2025
The extensive upgrades include three primary projects:
-
Majorstuen Station Upgrade: This project will see improvements to Majorstuen station, offering more access points, larger platforms, and a new pedestrian bridge.
-
Fornebu Line Connection: The Fornebu Line will be connected to the existing T-bane network.
- Signal and Security System Upgrade (CBTC): A new signal and security system will be installed.
Longest T-Bane Closure: Borgen to Majorstuen
The longest T-bane closure in 2025 will affect passengers traveling between Borgen and Majorstuen. Bus services will replace the T-bane from late March until early November.
Majorstuen Station Summer Closure
The Majorstuen station will be closed in several phases throughout the year. The station will remain closed primarily during the summer holidays when passenger volumes are typically lower.
Other Closures and Replacements
Ruter has provided a comprehensive overview of the closures. Key dates and affected lines include:
- January 4: Temporary closures on lines 1, 2, 3, 4, and 5 between various stations.
- March 28 – June 22: Closures on lines 2 and 3 between Borgen and Stortinget.
- July 5 – 25 & 26 – 27: Various lines closed, with some lines not operating at all.
- July 28 – August 3 & August 4 – September 6: Similar closures as in late July, affecting different lines.
- September 7 & 8 – November 3: More closures, including Majorstuen station shut-downs on September 8 and continuing until November 3.
- September 22 – November 3: Lines 2 and 3 closed between Borgen and Stortinget.
In addition to these dates, there may be closures on specific sections after 9 PM on certain days.
Ruter understands the frustration these closures may cause and assures passengers that they are working diligently to provide robust and efficient replacement services. The company will provide timely updates via their app and website.