3 Baltic PMs Reaffirm Full Support for Rail Baltica Project

The prime ministers of Estonia, Latvia, and Lithuania have reaffirmed their collective support for Rail Baltica during an online meeting, agreeing to target an opening window of 2028-2034 for the 870km standard-gauge railway connecting the Baltic states to mainland Europe.

Funding Goals and Budget Targets for the 870km Railway

The Baltic states aim to secure €10bn of funding from the European Union’s Connecting Europe Facility to complete the project. According to Latvian Prime Minister Andris Kulbergs, following an extraordinary Cabinet meeting, the Latvian government set a maximum cost ceiling of 20 million euros per kilometre for the railway project based on a study by independent consultants. This figure excludes major structures but covers tracks, electrification, and signalling necessary for a train to physically run along the main line. Up to this point, the cost per kilometre had ranged from 28 million to 32 million euros.

The total cost of Rail Baltica across the Baltic states could reach 23.8 billion euros, compared with a 2017 cost-benefit analysis estimate of 5.8 billion euros. The first phase, connecting the Baltic states to Europe with a single track, is estimated at 15.3 billion euros, though the Latvian Ministry of Transport told Latvian Radio that Latvia’s first phase could cost 7.5 billion euros, representing an increase of approximately two billion euros compared to forecasts from a few years prior.

Did You Know? In December 2023, Eiropas dzelzceļa līnijas and the E.R.B. Rail JV consortium—consisting of France’s Eiffage Génie Civil, Poland’s Budimex, and Italy’s Rizzani de Eccher—signed a 3.7 billion euro contract for construction of the Rail Baltica main line outside the city limits of Riga, covering approximately 200 kilometres of infrastructure.

Andris Kulbergs
Photo: Baltic News Network

Deadlines and Divergent Schedules Across the Baltic States

While the three Baltic prime ministers agreed to extend the deadline for the first phase of the project until 2034, Lithuania is maintaining its original 2030 deadline for its section. Lithuanian Transport Minister Juras Taminskas stated that the country aims to complete the section from Kaunas to Panevezys by 2030, citing the project’s importance for connectivity, security, military mobility, and economic competitiveness. Mindaugas Ivanavicius, head of Rail Baltica in Lithuania, noted that infrastructure arm LTG Infra is maintaining its work pace across design, procurement, and construction on the 392-kilometre Lithuanian section.

Political unity for Rail Baltica follows a tumultuous period in which politicians from Estonia, Latvia, and Lithuania questioned the line’s viability. Latvia previously commissioned an external study indicating that the scheme was unaffordable, leading to widespread speculation over cost reviews. Marko Kavila, CEO of delivery body RB Rail, defended the project in an IRJ interview this summer, rejecting assertions that major cost savings were possible without canceling construction entirely. Despite this, the Baltic prime ministers stated in a joint declaration that the project must achieve meaningful cost reduction to deliver the first phase.

3 Baltic PMs Reaffirm Full Support for Rail Baltica Project
Photo: Inbox

Next Steps for Construction and Brussels Negotiations

Construction work currently underway will continue as planned. However, future construction schedules for other line sections, investment priorities, and financing needs will be jointly agreed upon by the Baltic states and coordinated with the European Commission and Poland.

Latvian Prime Minister Andris Kulbergs indicated that he must travel to Brussels for the European Council to defend national positions on the upcoming European budget, identifying Rail Baltica as a key issue requiring clear and consistent funding. Meanwhile, the Latvian Ministry of Transport must draw up a minimum project scenario by December to determine actual first-phase costs and review obligations under existing contractor agreements.

Baltic Leaders Target Twenty Twenty-Eight to Twenty Thirty-Four for Railway Opening

What is the total length and route of Rail Baltica?

The project involves constructing a new 870-kilometre European-standard-gauge railway line linking Tallinn, Parnu, Riga, Panevezys, Kaunas, Vilnius, and Warsaw.

3 Baltic PMs Reaffirm Full Support for Rail Baltica Project
Photo: eng.lsm.lv

What are the revised timelines for opening the railway?

The Baltic prime ministers agreed to target the EU budgetary period of 2028-2034 for opening the main line, officially acknowledging a shift from the original 2030 target, though Lithuania maintains its 2030 goal for the Kaunas-Panevezys section.

How much will the project cost according to recent estimates?

The total cost across the Baltic states could reach 23.8 billion euros, with the first-phase cost estimated at 15.3 billion euros, while Latvia has separately instituted a maximum cost ceiling of 20 million euros per kilometre for main-line tracks, electrification, and signalling.